State of Hawai`i, Department of Land and Natural Resources |
![]() |
Kuhio Beach Nourishment Project
STATUS: Completed
Project Summary (pdf file 1.0 mb)
UPDATE: January 5, 2007.
Dredging completed. Barge and pipeline system demobilized and settling basin is backfilled and graded. Final beach grooming and grading should be completed by Saturday January 6, 2007.
Pumping started on Saturday Dec 4. Dredged sediment is well-sorted medium sand characterized by a gray color, lack of discernable odor, and is likely to be stable on the beach. Exposure to air and sunlight, and mixing with ambient sand, is expected to eventually lighten the color. Staging area and settling basin expanded to accomodate higher pumping rates. Sand distribution started Dec 7 sand has been delivered to the Diamond Head end of the Kuhio Swim basin sand distribution will begin in the Ewa swim basin (Area 2) starting Friday Dec 22.
Project Goal 10,000 yd
Sand Pumping Progress (Estimated- not including sand in settling basin berm)| Date | Estimated Pumped |
Daily Placed |
Total Placed (yd3) |
Comments |
| 12/4 | 10 | 0 | 0 | Testing |
| 12/5 | 10 | 0 | 0 | Testing |
| 12/6 | 380 | 0 | 0 | 1/2 day |
| 12/7 | 400 | 300 | 300 | 3/4 day |
| 12/8 | 0 | 420 | 720 | No Pumping |
| 12/11 | 400 | 0 | 720 | 1/2 day |
| 12/12 | 650 | 560 | 1280 | Full day |
| 12/13 | 500 | 520 | 1800 | Full day |
| 12/14 | 600 | 520 | 2320 | Full day |
| 12/15 | 600 | 600 | 2920 | Full day |
| 12/16 | 450 | 220 | 3140 | Full day |
| 12/20 | 0 | 560 | 3700 | No Pumping |
| 12/21 | 500 | 0 | 3700 | Full day |
| 12/22 | 500 | 370 | 4070 | Full day- Starting on Ewa Basin |
| 12/23 | 700 | 0 | 4070 | 1/2 Day |
| 12/26 | 450 | 510 | 4580 | 1/2 Day |
| 12/27 | 750 | 585 | 5165 | Full Day |
| 12/28 | 800 | 640 | 5805 | Full Day |
| 12/29 | 800 | 725 | 6530 | Full Day |
| 12/30 | 500 | 0 | 6530 | Full Day- Dredging completed |
| 1/2/07 | 0 | 880 | 7410 | No dredging (Basin deconstructed) |
| 1/3/07 | 0 | 780 | 8190 | Finish grading- no dredging |
| 1/4/07 | 0 | 1045 | 9235 | Finish grading- Sand to Site 3 |
| 1/5/07 | 0 | 765 | 10000 | Finish grading- Sand to Site 3 |
| Totals | 9000 | 10000 | 10000 | Totals |
Waikiki Beach Site Photos (December, 2006)
Blessing by Kahu Sherman Thomson
Existing, pumped & mixed sand
PRESS RELEASES:
January 05, 2007 KUHIO BEACH RESTORATION SUCCESSFULLY CONCLUDES
November 27, 2006 SET-UP FOR SAND PUMPING PROJECT GETS UNDERWAY AT KUHIO BEACH (pdf 28kb)
KUHIO BEACH- BACKGROUND INFORMATION (pdf 28kb)
Click here for daily water quality resultsClick here for additional project information and diagrams